Fixed
Pavement surface breaking up
Reported via mobile in the Public footpath or cyclepath category anonymously at 22:27, Thu 12 May 2022
Sent to Peterborough City Council less than a minute later. Council ref: 3522291.
The pavement/cycle path near this lampost on sargeants way is breaking up all along this section. Lots of cycles use this path at high speed and it is becoming increasingly dangerous with pot holes and loose tarmac
Updates
-
Thanks for making your report.
It will be passed on to the relevant department. We will endeavour to provide you with an update within 10 working days.
Posted by Peterborough City Council at 22:27, Thu 12 May 2022
-
The Peterborough City Council Highways team have assessed this issue as a low priority and aim to repair it within 3 to 6 months.
State changed to: Action scheduled
Posted by Peterborough City Council at 12:39, Thu 26 May 2022
-
The Peterborough City Council Highways team have assessed this issue as a medium priority and aim to repair it within 2 months.
Posted by Peterborough City Council at 12:40, Thu 26 May 2022
-
The works regarding this report have been completed. Please be aware that this job may be a temporary fix.
State changed to: Fixed
Posted by Peterborough City Council at 10:50, Wed 1 June 2022
This report is now closed to updates. You can make a new report in the same location.